Given this information, which of the following is the SLE?

An organization is looking to build its second head ofce in another city. which has a history of ooding with an average of two oods every ‘I00 years. The estimated building cost is $1 million. and the estimated damage due to flooding is half of the buildings cost.

Given this information, which of the following is the SLE?
A . $50,000
B . $200000
C . $500,000
D . $1.000000

Answer: C

Latest SY0-501 Dumps Valid Version with 1130 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments