For which objects can you perform budget availability control? (Choose two.)
For which objects can you perform budget availability control? (Choose two.)
A . Internal Order
B. Profit Center
C. Project
D. Cost Center
Answer: A,D
Explanation:
Reference: https://blogs.sap.com/2019/12/24/budget-availability-control-for-cost-centers-in-sap-s-4hana-1909/