For which object do you maintain the activity price to perform activity allocation?

For which object do you maintain the activity price to perform activity allocation?
A . Cost center
B . Profit center
C . Key figure
D . Internal order

Answer: A

Explanation:

Reference: https://erproof.com/co/sap-co-training/sap-direct-activity-allocation/