A . Earned value – tracking spend to assess delivery progress.
B . Benefits realisation – tracking whether the project has achieved the business case.
C . Resource management – tracking whether the project team is meeting utilisation targets.
D . Budget tracking – monitoring actual spend against planned spend.
Answer: A
Explanation:
Earned Value: This is a key performance indicator (KPI) in project management that integrates cost, scope, and schedule. It provides a clear view of how much progress has been made against the work planned and money spent.
Unsuitable Options:
B: Benefits realization assesses post-project success, not ongoing progress.
C: Resource management is unrelated to deliverables progress.
D: Budget tracking only measures financial health without linking to project outputs.