Which of the following is the BEST action for the project manager to take?
An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?A . Exploit the risk. B. Accept the risk. C. Avoid the risk. D. Transfer the risk.View AnswerAnswer: A Explanation: The project manager should exploit the...
Which of the following should have been considered during initial planning to prevent this situation?
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have...
Which of the following activities still needs to be performed to complete the schedule?
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?A . Allocate resources. B. Determine...
Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated...
Which of the following is the NEXT step for the project manager?
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?A . Update the project charter. B. Determine budget constraints. C. Create a project schedule D. Validate the business case.View AnswerAnswer: A Explanation: Update the project charter. Updating...
During a gate review meeting, the deliverable was rejected by the customer.
During a gate review meeting, the deliverable was rejected by the customer. INSTRUCTIONS Review the dashboard. * Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. * Part 2: Select the proper document(s) to be updated. If at any...
Which of the following can use the survey results as an input?
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?A . Daily stand-up B. Project momentum C. Performance feedback D. Meeting minutesView AnswerAnswer: C Explanation:...
Which of the following tools is the project manager using?
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?A . Multiauthoring software B. Word processor C. Real-time polling D. Conferencing platformsView AnswerAnswer: A Explanation: The project manager is using multiauthoring software to...
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
Which of the following criteria would favor using the agile methodology to manage an upcoming project?A . Strong projectized organization B. Medium risk C. Lack of resources D. Multiple undefined tasksView AnswerAnswer: D Explanation: Multiple undefined tasks would favor using the agile methodology to manage an upcoming project. Agile methodology...
A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:
A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:A . ROI. B. SOW. C. RFI. D. RPRView AnswerAnswer: A Explanation: The output...