Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?

A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?A . ConfidentialityB . CriticalityC . FrequencyD . Cultural differencesView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,...

July 28, 2022 No Comments READ MORE +

When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?

A project team is comprised of a mix of in-house and virtual team members. When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?A . Composing a project team email with the details of the...

July 28, 2022 No Comments READ MORE +

Which of the following should the project manager do to obtain the resources?

The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources. Which of the following should the project manager do to obtain the resources?A . The project manager should identify and document the reasons for the additional resources in a...

July 28, 2022 No Comments READ MORE +

Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes?

A stakeholder is unaware of a project’s status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)A . Status reportB . Organizational chartC . RACI matrixD . Meeting minutesE . Communication planView AnswerAnswer: A,D Explanation: References: Kim Heldman,...

July 28, 2022 No Comments READ MORE +

Which of the following strategies is the project manager applying?

A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions. Which of the following strategies is the...

July 28, 2022 No Comments READ MORE +

Which of the following actions should the project manager take?

An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs. Which of the following actions should the project manager take?A . Submit a new change request.B . Initiate the...

July 27, 2022 No Comments READ MORE +

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well. The project manager should:A . follow the change process flow and notify the legal department after the...

July 27, 2022 No Comments READ MORE +

Which of the following would be BEST suited to contribute cost and time estimates for the project activities?

A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities?A . Project team membersB . Project sponsorC . Project managerD . Project schedulerView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd...

July 27, 2022 No Comments READ MORE +

Which of the following risk strategies is the project manager applying?

A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?A . TransferB . AcceptC . AvoidD . MitigateView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238

July 27, 2022 No Comments READ MORE +

Which of the following is a necessary step to record the actual durations?

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?A . Establish each WBS work package resource.B . Establish and set the baseline.C . Establish and set the...