Question #1

You are designing distribution for a seven unit townhouse with in slab conduits.

What is the MINIMUM number of 27 mm (1 in) rigid PVC Type 2 or metallic conduit that is required to satisfy distribution to each unit?

  • A . Three
  • B . Four
  • C . Five
  • D . Seven
  • E . Fourteen

Reveal Solution Hide Solution

Correct Answer: D
Question #2

You have just finished a design calling for 15 telecommunications outlets. You received word that the owner has increased his requirements by 40%.

What size commercial DD (distribution device) is required to accommodate the increase?

  • A . 660 mm (26 in)
  • B . 1015 mm (40 in)
  • C . 1346 mm (53 in)
  • D . 1676 mm (66 in)

Reveal Solution Hide Solution

Correct Answer: C
Question #3

Which service is NOT typical of Grade 1?

  • A . Telephone
  • B . Multimedia
  • C . Data
  • D . Television

Reveal Solution Hide Solution

Correct Answer: B
Question #4

You are designing a multi-story dwelling and need to place the CTR’s. Every floor is not available.

What is the alternate spacing for the CTRs?

  • A . Every 2 floors
  • B . Every 3 floors
  • C . Every 4 floors
  • D . Every 5 floors
  • E . 1st floor and midway up through the height of the building

Reveal Solution Hide Solution

Correct Answer: B
Question #5

You are designing a system requiring the transmission of data. Your system must perform higher than ________ kHz in order to do so.

  • A . 4
  • B . 8
  • C . 10
  • D . 16
  • E . 32

Reveal Solution Hide Solution

Correct Answer: C
Question #6

To accommodate telephone, data, CATV, security and multimedia, a MINIMUM of ________ strands of optical fiber auxiliary disconnect outlet (ADO) cable should be provided.

  • A . Two
  • B . Four
  • C . Five
  • D . Six
  • E . Eight

Reveal Solution Hide Solution

Correct Answer: B
Question #7

Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?

  • A . PERT
  • B . Calendar
  • C . Milestone
  • D . Gantt

Reveal Solution Hide Solution

Correct Answer: A
Question #8

Which requirement does the ICT distribution designer provide to the Mechanical Engineer in charge of the HVAC design for a Telecommunication Space?

  • A . The heat load (BTU (calories/hour) of all equipment installed within the space
  • B . Location of the telecommunications own dedicated electrical distribution panel
  • C . The quantity and size of HVAC vents needed for the room
  • D . Location and size of condensate drain

Reveal Solution Hide Solution

Correct Answer: A
Question #9

Which of the following is a consideration for lighting telecommunication spaces?

  • A . To ensure worker safety within TEs. Light level requirements are higher tor these than other spaces
  • B . The light fixtures within telecommunications spaces shall be fluorescent type fixtures.
  • C . The electrical power for lighting shall be connected to the same electrical panel as the telecommunications equipment.
  • D . The lighting layout shall be coordinated with the equipment and pathway locations

Reveal Solution Hide Solution

Correct Answer: D
Question #10

In a budding with one join room for serving as the FR and EF and four dedicated TRs on the same floor a total of__________ 103 mm (4 trade size) conduits should be installed to interconnect the backbone pathways to the ER.

  • A . 4
  • B . 8
  • C . 16
  • D . 20

Reveal Solution Hide Solution

Correct Answer: C

Question #11

What is used to facilitate MINOR changes to the Project Requirements?

Request lot Information (RFI)

  • A . Punch list
  • B . Field order
  • C . Change order
  • D . Change order request

Reveal Solution Hide Solution

Correct Answer: C
Question #12

Which two of the following types of metallic conduit REQUIRE threaded couplings? (Select two options.)

  • A . Electrical metallic tubing (EMT)
  • B . Aluminum metal conduit (AMC)
  • C . Flexible metal conduit (FMC)
  • D . Intermediate metal conduit (IMC)
  • E . Rigid metal conduit (RMC)

Reveal Solution Hide Solution

Correct Answer: D, E
Question #13

When considering pathway types, the ICT distribution designer should consider the applicable MICE factors as defined in TIA 568 for structured cabling systems and components MICE 3 relates to

  • A . commercial environment
  • B . heavy industrial environment
  • C . medical environment
  • D . light industrial environment

Reveal Solution Hide Solution

Correct Answer: A
Question #14

An ICT distribution designer is representing a client during a project execution.

What is the designer’s role in the Vendor and Contractor Coordination?

  • A . Oversee the sequence of the work and ensure that the job proceeds as anticipated in accordance with the project execution schedule
  • B . Synchronizes the daily activities of all trades through daily or weekly meetings (depending on project size, complexity, or criticality) with individual trade PMs. Fore people, supervisors and designers as necessary
  • C . Holds two critical meetings to begin the project and allow all parties to introduce themselves
    The first meeting usually is conducted with the owner and design team, and the second meeting is with the field personnel and subcontractors
  • D . lf specific questions arise regarding coordination of the installation with structural, architectural, and site conditions and work between trades, submit RFIs to the GC with appropriate documentation to demonstrate the concern along with the proposed installation.

Reveal Solution Hide Solution

Correct Answer: D
Question #15

An ICT distribution designer is designing a backbone cabling network that is specified for a campus network including several links approaching 2000 m (6562 It) and data rates of 100 Gb/s What optical fiber type(s) should be used?

  • A . OM3 fiber
  • B . OM4 fiber
  • C . Both OS1 and OS2 fiber
  • D . Both OS2 and OM3 fiber

Reveal Solution Hide Solution

Correct Answer: C
Question #16

What is the MAXIMUM recommended length for A in the image below?

  • A . 70 m (230 ft)
  • B . 90 m (295 ft)
  • C . 100 m (320 ft)
  • D . 150 m (495 ft)
  • E . 300 m (985 ft)

Reveal Solution Hide Solution

Correct Answer: B
Question #17

Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?

  • A . Verify the equipment controls are in the proper operating position.
  • B . Train workers to perform the LOTO process.
  • C . Apply appropriate tags both locally and remotely.
  • D . Confirm the device is de-energized by proving it will not run when started.
  • E . Confirm all unnecessary items have been removed from the area.

Reveal Solution Hide Solution

Correct Answer: C
Question #18

The type of apparatus housed in TRs varies greatly in size, purpose and function.

Which two of the following active equipment is included? (Select two options.)

  • A . Cross-connect facilities
  • B . Telecommunication’s equipment
  • C . Environmental controls
  • D . Lighting controls
  • E . Building system equipment

Reveal Solution Hide Solution

Correct Answer: B, E
Question #19

A design build firm has been retained by a client to construct an outpatient clinic. The client has hired an ICT distribution designer to review the DB firm’s work product ensuring that the certified (mat documents are complete. In what capacity would the designer MOST LIKELY be serving?

  • A . Quality Assurance (QA)
  • B . ICT Designer of Record (DOR)
  • C . Project Management (PM)
  • D . Quality Control (QC)

Reveal Solution Hide Solution

Correct Answer: A
Question #20

In specifying labels and pruned tags that meet Underwriters Laboratories (UL) 969 Standard, marking and labeling systems are provided following the listed metrics.

Which two of the following are REQUIRED for the UL standard? (Select two options.)

  • A . Adhesion test
  • B . Thickness test
  • C . Texture test
  • D . Durability test
  • E . Visual inspection

Reveal Solution Hide Solution

Correct Answer: A, E

Question #21

When designing cable tray pathways under an access floor, what is the MINIMUM free space that should exist between the top of the cable tray side rails and the underside of the stringers?

  • A . 25 mm (1 in)
  • B . 51 mm (2 in)
  • C . 71 mm (3 in)
  • D . 101.60 mm (4 in)

Reveal Solution Hide Solution

Correct Answer: B
Question #22

A voice over IP network that converges voice capabilities with softphones. Video communications, instant messaging is referred to as

  • A . Ethernet network communications
  • B . unified communications.
  • C . mesh communications services
  • D . converged communications
  • E . unified fabric architecture

Reveal Solution Hide Solution

Correct Answer: B
Question #23

The options for termination an unshielded twisted pair cable for a video surveillance camera at the camera end are an 8-pin 8 conductor outlet and

  • A . 8-pin 8-contact plug.
  • B . 75 ohm balun
  • C . 50 ohm balun
  • D . biscuit jack
  • E . shielded RJ-45 connector

Reveal Solution Hide Solution

Correct Answer: A
Question #24

When sizing an underground entrance facility, what is the MINIMUM amount of 103 metric designator conduits (4 trade size) that should be specified by the ICT distribution design?

  • A . 2 Conduits
  • B . 3 Conduits
  • C . 4 Conduits
  • D . 6 Conduits

Reveal Solution Hide Solution

Correct Answer: C
Question #25

Which of the following is TRUE for tele communications spaces?

  • A . Maintain aim (3.28 ft) clearance between equipment and plumbing fixtures such as mop sinks
  • B . Plumbing piping not related to the support of the space should not pass through the space.
  • C . Relative humidity snail be maintained at 40% ± 5%.
  • D . Close proximity to water service is desired so consider locating the ER in the pipe chase.

Reveal Solution Hide Solution

Correct Answer: B
Question #26

What is the MINIMUM fire rating for telecommunications spaces walls and wall linings, if not specified otherwise by local Authority Having Jurisdiction (AHJ)?

  • A . One hour
  • B . Two hours
  • C . Three hours
  • D . No minimum requirement

Reveal Solution Hide Solution

Correct Answer: B
Question #27

In a PTP network using optical fiber, the ________ is responsible for media conversions from the optical fiber to the balanced twisted pair network within the residence.

  • A . ONU
  • B . OS
  • C . ONT
  • D . OLT
  • E . OLTS

Reveal Solution Hide Solution

Correct Answer: C
Question #28

When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams lo integrate logical activities and identify critical paths on the project? (Select two options.)

  • A . If This Then That (IFTT)
  • B . Gantt Chart
  • C . Work Breakdown Structure (WBS)
  • D . Critical Path Method (CPM)
  • E . Program Evaluation Review Technique (PERT)

Reveal Solution Hide Solution

Correct Answer: B, D
Question #29

For optical fiber cabling, which of the following test instruments is used to locate and identify any anomalies?

  • A . OTDR
  • B . Optical power meter
  • C . OLTS
  • D . Spectrum analyzer

Reveal Solution Hide Solution

Correct Answer: A
Question #30

In which of the following design phases does the ICT distribution designer perform coordination with stakeholders and other disciplines (e.g.. mechanical, architectural, electrical) to ensure that the design is constructive and that any conflicts are resolved early in the process?

  • A . Concept Design
  • B . Design Development (DD)
  • C . Schematic Design (SD)
  • D . Construction Document (CD)

Reveal Solution Hide Solution

Correct Answer: B

Question #31

When designing horizontal pathways, the ICT distribution designer should consider the design’s ability to (Select two options.)

  • A . handle only the day one needs as the future is unknown.
  • B . minimize occupant disruption when horizontal pathways are accessed.
  • C . handle at least 3 different cabling media types.
  • D . accommodate cabling changes
  • E . accommodate at least 50 percent future growth

Reveal Solution Hide Solution

Correct Answer: B, D
Question #32

For a six story building (plus a basement) each of the six floors has a useable area of =3716 m2 (40.000 ft2) There are two riser systems, each serving halt of the useable area on each Moor What are the sleeves quantity and configuration required from fifth floor to sixth floor?

  • A . Two sleeves
  • B . Three sleeves
  • C . Four sleeves
  • D . Five sleeves

Reveal Solution Hide Solution

Correct Answer: D
Question #33

An ICT distribution designer is estimating the installation of five units of 1.5 m (5 ft) tong channel basket trays connected together in the ceiling. The total length of the pathway needed is 7 5 m (25 ft).

How many supports will be needed”

  • A . 2
  • B . 5
  • C . 7
  • D . 10
  • E . 20

Reveal Solution Hide Solution

Correct Answer: B
Question #34

Which of the following is TRUE about convenience receptacles?

  • A . They are duplex or quad receptacles mounted on perimeter walls.
  • B . They must be powered by emergency power to prevent loss of service.
  • C . They shall be connected to occupancy sensors to ensure user safety.
  • D . They increase the count of outlets needed on the equipment racks.
  • E . They are those into which equipment, such as switches, shall be plugged

Reveal Solution Hide Solution

Correct Answer: A
Question #35

Which of the following is a common application for exothermic welding of earthing (grounding) and bonding conductors?

  • A . Bonding to structural steel
  • B . Locations requiring monthly maintenance
  • C . Connections made to the TBB
  • D . Cable to cable connections

Reveal Solution Hide Solution

Correct Answer: D
Question #36

Which of the following is the process of limiting fire and smoke using fire-resistive barriers?

  • A . Detection
  • B . Compart mentation
  • C . Suppression
  • D . Prevention

Reveal Solution Hide Solution

Correct Answer: A
Question #37

In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?

  • A . CD
  • B . SD
  • C . PD
  • D . DD

Reveal Solution Hide Solution

Correct Answer: B
Question #38

Conducted coupling may affect electronic devices primarily through which two of the following means’? (Select two options.)

  • A . inductive coupling (by magnetic fields)
  • B . Input signal lines
  • C . Output signal lines
  • D . Optical signal lines
  • E . Capacitive coupling (by electric fields)

Reveal Solution Hide Solution

Correct Answer: B, C
Question #39

Close out documentation is initially discussed in which of the following meetings?

  • A . Prime Contractor and Subcontractor Meetings
  • B . Kickoff Meeting
  • C . Weekly Progress Meetings
  • D . Vendor Meeting

Reveal Solution Hide Solution

Correct Answer: A
Question #40

An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building C. Both ends are terminated with SC connectors.

What is the loss budget for the above fiber link?

  • A . 2.95 dB
  • B . 3.40dB
  • C . 3.90 dB
  • D . 4.35 dB

Reveal Solution Hide Solution

Correct Answer: C

Question #41

In order for an ICT distribution designer to identify the BEST solutions for the client’s needs they may have to provide

  • A . Operation and Maintenance manuals
  • B . subcontractors lists
  • C . material lists (e.g., BOM).
  • D . shop drawings

Reveal Solution Hide Solution

Correct Answer: C
Question #42

What’s the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)

  • A . 305 mm(12 in)
  • B . 610 mm (24 in)
  • C . 914 mm (36 in)
  • D . 1270 mm (50 in)
  • E . Below the area’s 50-year frost line

Reveal Solution Hide Solution

Correct Answer: B, E
Question #43

DRAG DROP

Identify the fibers below as either single mode (SM) or multi-mode (MM) by dragging the appropriate term into each oval.

Reveal Solution Hide Solution

Correct Answer:


Question #44

An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer’s recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)

  • A . 0.006 m2 (8 in2)
  • B . 0.008 m2 (12 in2)
  • C . 0.040 m2 (60 in3)
  • D . 0.60 m2 (80 in3)

Reveal Solution Hide Solution

Correct Answer: B
Question #45

Open RFI’s should be reviewed on a _________basis.

  • A . daily
  • B . bi-weekly
  • C . weekly
  • D . bi-monthly

Reveal Solution Hide Solution

Correct Answer: C
Question #46

Which two of the following items MUST be included in a detailed SoW? (Select two options.)

  • A . What type of work needs to be performed
  • B . A general description of work to be performed
  • C . Who must approve the Scope of work
  • D . How the contract performance will be evaluated/judged
  • E . When the work will start

Reveal Solution Hide Solution

Correct Answer: A, E
Question #47

When designing an underground conduit system, a single bend should be NO MORE THAN ________ degrees.

  • A . 45
  • B . 75
  • C . 90
  • D . 120

Reveal Solution Hide Solution

Correct Answer: C
Question #48

What is the PRIMARY reason for considering a physical ting topology for connecting outlying buildings?

  • A . It is the most cost effective design ten a campus network.
  • B . It provides a redundant cable path for disaster recovery.
  • C . It is the most compelling design for any network requirement.
  • D . It is an easier physical design to install.

Reveal Solution Hide Solution

Correct Answer: B
Question #49

What is the MINIMUM lighting requirement (or telecommunications spaces?

  • A . 50 lux (4.6 toot-candles) of lighting in the horizontal plane and 20 lux (1.9 fool-candles) of lighting in the vertical plane measured al at 1 meter (3.28 feet) above the finished floor
  • B . 200 lux (18 6 fool-candles) of lighting In the horizontal plane and 500 lux (46 foot-candles) of lighting In the vertical plane measured at at 1 meter (3.28 feet) above the finished floor
  • C . 500 lux (46 foot-candles) of lighting in the horizontal plane and 200 lux (18 6 foot-candles) of lighting in the vertical plane measured at at 1 meter (3 28 feet) above the finished floor
  • D . 500 lux (46 foot-candles) of lighting in the horizontal plane and 500 lux (46 foot-candles) of lighting in the vertical plane measured at at 1 meter (3 28 feet) above the finished floor

Reveal Solution Hide Solution

Correct Answer: C
Question #50

During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and

  • A . cost projections.
    B OSHA specifications
  • B . client requirements
  • C . equipment availability

Reveal Solution Hide Solution

Correct Answer: C

Question #51

When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

  • A . Taxes
  • B . Permits
  • C . Inspection
  • D . Licensing
  • E . Safety

Reveal Solution Hide Solution

Correct Answer: B, C
Question #52

An ICT distribution designer is reviewing design documents with the owner to gam approval for an ER design.

Which of the following information about the site shall be included?

  • A . Sustainability requirements
  • B . Suitability requirements
  • C . Access and/or service provider requirements
  • D . Designer requirements

Reveal Solution Hide Solution

Correct Answer: C
Question #53

Which two of the following are ADVANTAGES of underground conduit systems? (Select two options.)

  • A . Provide additional physical cable protection
  • B . Not adaptable for future facility placement or removal without disturbing the property
  • C . Economical over a long life
  • D . Require more installation time than aerial or direct-buried installations
  • E . Route planning is not as critical as aerial or direct-burial

Reveal Solution Hide Solution

Correct Answer: A, C
Question #54

What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?

  • A . After the contract is awarded and before project close out
  • B . As part of the contract bid process to prevent project delays
  • C . Before the contract is awarded
  • D . At the beginning of the close out process

Reveal Solution Hide Solution

Correct Answer: A
Question #55

What is the MAXIMUM number of work areas served by a single Multiuser Telecommunications Outlet Assembly (MUTOA)?

  • A . 5
  • B . 10
  • C . 12
  • D . 18

Reveal Solution Hide Solution

Correct Answer: C
Question #56

Telecommunications systems typically combine multiple digital data streams into one data stream.

What is this process called?

  • A . Time division multiplexing (TDM)
  • B . Wave division multiplexing (WDM)
  • C . Coarse wave time division multiplexing (CWTDM)
  • D . Coarse wave division multiplexing (CWDM)

Reveal Solution Hide Solution

Correct Answer: A
Question #57

The transfer of unwanted signals may occur over one path or several paths.

What method addresses the mitigation or suppression of unwanted signals?

  • A . Mounting heights in racks and cabinets
  • B . Bonding and grounding
  • C . Signal coupling
  • D . The use of unshielded cables

Reveal Solution Hide Solution

Correct Answer: B
Question #58

A project’s closeout plan will be executed by the project manager (PM) and will be managed and approved by the

  • A . owner
  • B . contractor
  • C . lCT distribution designer
  • D . projects installation supervisor

Reveal Solution Hide Solution

Correct Answer: C
Question #59

In a PON deployment, which active device is installed at the work area?

Wireless access point

  • A . Optical amplifier
  • B . Optical line terminal
  • C . Optical network terminal
  • D . Splitter

Reveal Solution Hide Solution

Correct Answer: D
Question #60

When planning a telecommunication termination area, what is the estimated space needed to terminate 144 strands of optical fiber?

  • A . 6350.01 mm2 (250 in2)
  • B . 7315.21 mm2 (288 in2)
  • C . 8890.01 mm2 (350 in2)
  • D . 10972.82 mm2 (432 a)
  • E . 14376.43 mm2 (566 in2)

Reveal Solution Hide Solution

Correct Answer: B

Question #61

What’s the RECOMMENDED twisted pair cable slack length to be left at the work area outlet location to enable the possibility of future changes in the Horizontal Cabling System?

  • A . =0.152 m (0.5 ft)
  • B . =0.3 m (1 ft)
  • C . =1 m (3 ft)
  • D . = 5m (16 40 ft)

Reveal Solution Hide Solution

Correct Answer: B
Question #62

Which of the following statements Is CORRECT concerning best practice for horizontal cable management panels?

  • A . One RU of management panel for each RU of cable patch panel plus one additional RU of cable management
  • B . Two RU of cable management panel for each RU of patch panel
  • C . Three RU of cable management panel for each RU of patch panel
  • D . Two RUs of management panel for each RU of cable patch panel plus two additional RUs of cable management

Reveal Solution Hide Solution

Correct Answer: A
Question #63

Communicating a project’s design and technical specifications to the client and stakeholders is part of the ___________of the project.

  • A . scope of work
  • B . needs analysis
  • C . close out procedure
  • D . bidding phase

Reveal Solution Hide Solution

Correct Answer: A
Question #64

In a RFI, an ICT distribution designer instructs the contractor to test all the fibers In a PON Installation.

Which of the following testing requirements does the designer include?

  • A . Uni-directional 850 nm and 1300 nm
  • B . Bi-directional 850 nm and 1300 nm
  • C . Uni-directional 1310 nm and 1550 nm
  • D . Bi-directional 1310 nm and 1550 nm

Reveal Solution Hide Solution

Correct Answer: D
Question #65

When designing a video communications network, which type of video communication link is two-person videoconferencing?

  • A . Point-to-multipoint bidirectional
  • B . Point-to-multipoint unidirectional
  • C . Unidirectional
  • D . PTP unidirectional
  • E . PTP bidirectional

Reveal Solution Hide Solution

Correct Answer: D
Question #66

The ICT distribution designer is hired to design a Telecommunications Room on the third floor of a building. The size of the floor is 20 m by 26 m (92 x 85 It).

What is to be the MINIMUM size of the TR?

  • A . Shallow Room, no minimum room size
  • B . =3 m (10 ft) by = 2.40 m (8 ft)
  • C . =3 m (10 ft) by =2.74 m (9 ft)
  • D . =3 m (10 ft) by =3.40 m (11 ft)

Reveal Solution Hide Solution

Correct Answer: B
Question #67

During bidding the ICT distribution designer should review the bid responses for compliance and completeness. Afterwards, the designer should report the findings and recommendations to the

  • A . construction foreman
  • B . legal counsel
  • C . stakeholders
  • D . technical consultant

Reveal Solution Hide Solution

Correct Answer: C
Question #68

DRAG DROP

Identify the core switch(es) and server(s) of the data center in the diagram below by dragging the appropriate term into each box in the diagram.

Reveal Solution Hide Solution

Correct Answer:


Question #69

An RFQ usually provides more detail than RFP in selection material such as

  • A . delivery date
  • B . color
  • C . make
  • D . mounting option

Reveal Solution Hide Solution

Correct Answer: B
Question #70

A system integration approach of a BAS on to a LAN can usually reduce the cost of cabling-related changes by

  • A . 10 to 20 percent
  • B . 25 to 40 percent
  • C . 45 percent
  • D . 50 percent

Reveal Solution Hide Solution

Correct Answer: B

Question #71

Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)

  • A . Schedule
  • B . Contract administration
  • C . Legal matters
  • D . Technical considerations
  • E . Financial matters

Reveal Solution Hide Solution

Correct Answer: A, D
Question #72

Which of the following team members is responsible for ensuring compliance with me contract documents (CDP

  • A . Owner
  • B . lCT Distribution Designer
  • C . Architect
  • D . Construction Manager (CM)

Reveal Solution Hide Solution

Correct Answer: B
Question #73

In a design type Scope of Work (SoW) the ICT distribution designer is responsible for providing

  • A . stakeholder requirements
  • B . a safety plan
  • C . a user needs analysis
  • D . specific products and materials

Reveal Solution Hide Solution

Correct Answer: D
Question #74

The marketing department of a firm has tasked the organization to design a structured cabling system allowing them to support either 10G6aseT or HDBASE-T. The budget requires that only one cable type be installed and that it be MINIMUM compliant. Of the following choices, what is the choice with the MINIMUM solution/solutions for the client?

  • A . Category 5e
  • B . Category 6
  • C . Category 6A
  • D . Category 7

Reveal Solution Hide Solution

Correct Answer: C
Question #75

What category/class of cabling does BICSI recommend for the MINIMUM performance level of horizontal balanced twisted-pair cabling?

  • A . Category 5e/class D
  • B . Category 6/class E
  • C . Category SA/class EA
  • D . Category 7/class F

Reveal Solution Hide Solution

Correct Answer: B
Question #76

Who prepares the submittals that are reviewed and approved to ensure that the clients design criteria is met in regards to material selection?

  • A . General Contractor
  • B . ICT distribution designer
  • C . Client
  • D . Architect. Engineering, Consultant Team

Reveal Solution Hide Solution

Correct Answer: A
Question #77

Which two of the following roles do an ICT distribution designer use to ensure a timely and cost-effective telecommunications construction project? (Select two options.)

  • A . Discuss design concerns with inspectors. AHJs, and other stakeholders.
  • B . Verify that the overall physical security design complies with the owner expectations.
  • C . Assist in the resolution of unforeseen conditions, change orders RFIs and changes to the project’s critical path.
  • D . Ensure the construction materials are stored properly and protected from theft.
  • E . Coordinate electrical supply so it is available in advance of the starting of contractor work.

Reveal Solution Hide Solution

Correct Answer: C, D
Question #78

A 3 trade size conduit is sized at

  • A . 78 mm (3 in)
  • B . 91 mm (3 1/2 in)
  • C . 103 mm (4 in)
  • D . 129 mm (5 in)

Reveal Solution Hide Solution

Correct Answer: A
Question #79

Which of the following options BEST describes Request for Quote (RFQ)?

  • A . Usually provides more detail involved with selecting the material, equipment, and components required during implementation (e.g. make, model, performance specifications)
  • B . Can be submitted by the contractor in response to a field order or as an uninitiated request for a change in scope
  • C . Used to obtain a formal response to the contract documents
  • D . An invitation for the design professionals (e g, architect, engineer, consultant) or contractors to submit a proposal for services

Reveal Solution Hide Solution

Correct Answer: A
Question #80

Which of the following transmitter light sources has a MINIMUM bandwidth of 4700 MHz/km (EMB) at 850 nm">

  • A . OM1 (62 50/125 multimode)
  • B . OM2 (50/125 multimode)
  • C . OM3 (50/125 laser optimized multimode)
  • D . OM4 (50/125 laser optimized multimode)

Reveal Solution Hide Solution

Correct Answer: D

Question #81

A project’s installation start involves a Kickoff Meeting and the General Contractor’s Coordination Meeting. As part of the designer’s responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)

  • A . Project submittal approval process
  • B . RFI process
  • C . Payment procedures
  • D . Punch List process
  • E . Project start and completion dates

Reveal Solution Hide Solution

Correct Answer: B, E
Question #82

An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passive optical splitter

  • A . 8
  • B . 16
  • C . 32
  • D . 64

Reveal Solution Hide Solution

Correct Answer: B
Question #83

What is the RECOMMENDED bend radius of a conduit with an internal diameter of 51 mm (2 in)?

  • A . 203 mm (8 in)
  • B . 305 mm (12 in)
  • C . 406 mm (16 in)
  • D . 508 mm (20 in)

Reveal Solution Hide Solution

Correct Answer: D
Question #84

Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly.

Which two of the following conditions could be caused by a poorly supported cabled (Select two options.)

  • A . Lower dB loss values
  • B . Stretching of copper conductors and breakage of optical fiber strands
  • C . Increased Interference levels
  • D . Reduced expected useful life and performance
  • E . Slippage between the cable core and the sheath

Reveal Solution Hide Solution

Correct Answer: B, E
Question #85

The MINIMUM required for backbone floor to floor pathways is five (5) sleeves each being 103 mm (four trade size) in diameter What increase in usable floor space should another 103 mm (four trade size) sleeve be added?

  • A . =929 m2 (10,001 ft2)
  • B . =1858m2 (20,001 ft2)
  • C . =3716 m2 (40,001 ft2)
  • D . =4645 m2 (50,001 ft2)

Reveal Solution Hide Solution

Correct Answer: C
Question #86

An ICT distribution designer is reviewing a client’s site information (spaces and pathways) to determine network technology and equipment selection. This is referred to as a___________design process

  • A . logical network
  • B . top-down
  • C . bottom-up
  • D . functional

Reveal Solution Hide Solution

Correct Answer: C
Question #87

Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect

  • A . Authority
  • B . Having Jurisdiction (AHJ)
  • C . Construction Manager
  • D . ICT Distribution Designer/Project Manager

Reveal Solution Hide Solution

Correct Answer: D
Question #88

The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system.

What is the MINIMUM trade size of sleeves recommended to serve a TR, ER, or EF?

  • A . 2
  • B . 4
  • C . 6
  • D . 8

Reveal Solution Hide Solution

Correct Answer: B
Question #89

Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)

  • A . Proximity to interfering sources
  • B . Missing or inadequate optical connections
  • C . Missing or inadequate device or cable shielding
  • D . Interface designs
  • E . Input signal lines

Reveal Solution Hide Solution

Correct Answer: A, C
Question #90

What step can be a phase of the Bidding and Negotiating process?

  • A . Prepare necessary change orders
  • B . Identifying any conflicts that may become apparent
  • C . Creating a response evaluation
  • D . Identifying potential value engineering opportunities

Reveal Solution Hide Solution

Correct Answer: C

Question #91

How many classes of telecommunications administration are there?

  • A . 3
  • B . 4
  • C . 5
  • D . 6

Reveal Solution Hide Solution

Correct Answer: B
Question #92

For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a

  • A . SoW.
  • B . spare ad sheet
  • C . worksheet
  • D . database

Reveal Solution Hide Solution

Correct Answer: A
Question #93

Based on the estimated work area size, what is the MAXIMUM number of work areas that a telecommunications enclosure shall serve?

  • A . 20
  • B . 26
  • C . 32
  • D . 36
  • E . 40

Reveal Solution Hide Solution

Correct Answer: D
Question #94

Which two of the following are included in the ICT distribution designer’s role of vendor and contractor coordination’? (Select two options.)

  • A . Conduct final ICT inspections to ensure standard and code compliance, design intent, and/or client requirements are met.
  • B . Monitor project schedule for delays
  • C . Produce ICT closeout documentation for the owner to provide the record documentation of the installation
  • D . Communicate status to stakeholders
  • E . Assist in the resolution of unforeseen conditions, change orders. RFIs, and changes to the project’s critical path

Reveal Solution Hide Solution

Correct Answer: D, E
Question #95

Which of the following terms is often used to describe two parallel paths that have identical conductive terminations to two separate grounding reference points?

  • A . Resistive loop
  • B . Ground loop
  • C . Capacitive loop
  • D . Inductive loop
  • E . Conductive loop

Reveal Solution Hide Solution

Correct Answer: B
Question #96

Which two of the following may the ICT distribution designer need to provide in order to identify the BEST solutions for the client’s need? (Select two options.)

  • A . Preliminary budget numbers
  • B . Color scheme for dropcables
  • C . Documentation plan
  • D . Recommendations for label design of outlets
  • E . Time constraints and/or milestones

Reveal Solution Hide Solution

Correct Answer: A, E
Question #97

When designing for horizontal pathways in an environment that requires fire-stopping for penetrating a rated wall, what is the MAXIMUM till ratio for telecommunications cabling in a cable tray?

  • A . 20 percent
  • B . 40 percent
  • C . 50 percent
  • D . There is no fill ratio for cable tray

Reveal Solution Hide Solution

Correct Answer: B
Question #98

In a contiguous properly environment (e. g., where campus backbone cables exist), which two of the following are CRITICAL factors to understand for maintenance and growth purposes? (Select two options.)

  • A . Fill ratio
  • B . Familiarity with the routes and spaces (proper record keeping)
  • C . Cable composition
  • D . Not able to determine the working capacity versus spare cable capacity
  • E . Cost analysis of the value of capex and capex models

Reveal Solution Hide Solution

Correct Answer: B, C
Question #99

ICT project installation issues that require coordination with mechanical, electrical and/or other "trades" can be BEST accomplished by

  • A . coordinating with the job site supervisors
  • B . issuing an RFI to the General/Prime Contractor
  • C . texting or calling the General/Prime Contractor
  • D . issuing a Change Order

Reveal Solution Hide Solution

Correct Answer: B
Question #100

For the MAXIMUM flexibility of a cabling system in a hierarchical star topology, ALL backbone cables and links to FR’s should be terminated at the

  • A . HC (FD).
  • B . IC (BD).
  • C . TR
  • D . MC (CD)

Reveal Solution Hide Solution

Correct Answer: D
Exit mobile version