A program manager has a multiple-project program that is scheduled to be completed by year’s end. During the program delivery phases of the protects several mandatory changes are identified that would extend the program’s completion date
What is the next step for the program manager?
- A . Apply resource leveling to ensure the program is completed on schedule
- B . Update the schedule to reflect the extended completion date
- C . Adjust working hours to ensure the program is completed on schedule
- D . Submit a change request to extend the program schedule
Which of the following statements Is CORRECT concerning best practice for horizontal cable management panels?
- A . One RU of management panel for each RU of cable patch panel plus one additional RU of cable management
- B . Two RU of cable management panel for each RU of patch panel
- C . Three RU of cable management panel for each RU of patch panel
- D . Two RUs of management panel for each RU of cable patch panel plus two additional RUs of cable management
The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year. Where is this expectation documented1?
- A . Program quality standards
- B . Customer management plan
- C . Benefits management plan
- D . Benefits sustainment plan
Program A is dependent upon program B lo complete benefits sustainment for two benefits Program A is on track to meet program benefits However program B’s program manager has just advised that program B has been closed.
What should program A’s program manager update and review first with the stakeholders?
- A . Benefits sustainment plan
- B . Benefits register
- C . Benefits management plan
- D . Benefits transition plan
Close out documentation is initially discussed in which of the following meetings?
- A . Prime Contractor and Subcontractor Meetings
- B . Kickoff Meeting
- C . Weekly Progress Meetings
- D . Vendor Meeting
For a backbone distribution system serving a usable floor space of 8,920 m2 (96,000 ft2), the MINIMUM slot area to be used for this back bone is
- A . 0.040 m2 (60 in2)
- B . 0.048 m2 (72 in2)
- C . 0.056 m2 (84 in2)
- D . 0.064 m2 (96 in2)
Which two of the following components are included in a backbone distribution system (BDS)? (Choose two.)
- A . Work area outlets
- B . Telecommunications enclosures
- C . Equipment Cord
- D . Equipment rooms
- E . Horizontal Cable
A program manager prepares the program for review to secure funding by senior management.
Which of the following must the program manager identify when creating the program charter?
- A . Milestone dates, budget, and staff details that support it
- B . Assumptions incorporated into the benefits management plan
- C . Process within the organization that will be needed to deliver the product
- D . Key decision makers or stakeholders in the program and their expectations and interests
A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.
What should the program manager do NEXT?
- A . Consider the option to close out the key project
- B . Evaluate the program and re-baseline the objectives
- C . Assess the benefits and impact to the program.
- D . Amend the risk register with the key project changes
An ICT distribution designer is designing a backbone cabling network that is specified for a campus network including several links approaching 2000 m (6562 It) and data rates of 100 Gb/s
What optical fiber type(s) should be used?
- A . OM3 fiber
- B . OM4 fiber
- C . Both OS1 and OS2 fiber
- D . Both OS2 and OM3 fiber