A program to implement a company’s new system is nearing completion and the program manager attempts to close the program However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.
To prevent this concern in the future, which of the following should occur?
- A . Collaboration with the operational staff to develop the benefits sustainment plan
- B . Communication of the new capabilities" benefits to the operational staff
- C . Development and execution of a benefits transition plan to prepare the operational areas
- D . Identification of the risk in the program risk register and development of a plan to address the risk
A program manager is developing a program management plan by integrating the plans of constituent projects. During this effort, the program manager learns that a resource is critical to more than one component and there is a time overlap for their availability
When creating the program resource management plan, what should the program manager do first?
- A . Ask the human resource manager to hire an additional resource
- B . Revise the plan to ensure the allocation of all needed resources
- C . Analyze resource capacity and capability with component protect managers
- D . Develop the program schedule in accordance with resource availability
A design build firm has been retained by a client to construct an outpatient clinic. The client has hired an ICT distribution designer to review the DB firm’s work product ensuring that
the certified (mat documents are complete.
In what capacity would the designer MOST LIKELY be serving?
- A . Quality Assurance (QA)
- B . ICT Designer of Record (DOR)
- C . Project Management (PM)
- D . Quality Control (QC)