Which of the following terms is often used to describe two parallel paths that have identical conductive terminations to two separate grounding reference points?
- A . Resistive loop
- B . Ground loop
- C . Capacitive loop
- D . Inductive loop
- E . Conductive loop
Near the completion of a transformation program, the operations manager is concerned that their department failed lo be notified in advance of the new service being transitioned into operations. They claim that their department did not approve this service and is now unprepared and untrained to support the transformation.
What should the program manager have done first to prevent this?
- A . Added the operations manager as a key stakeholder
- B . Created a transition plan during the planning phase for the impacted operational area
- C . Ensured there was a communications management plan that included the transition to operations
- D . Drafted a training plan with assistance from the program management office (PMO) or human resource department before transitioning it to operations
The program manager has a global program with live component projects. The program sponsor wants the management plans, processes/procedures and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six months into a three-year program.
What should the program manager do next?
- A . Accept what the program sponsor requires and implement the changes
- B . Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor Die best option
- C . Respond to the program sponsor if the program sponsor asks about It a second time
- D . Present the risks and benefits of the changes to the program sponsor
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?
- A . Program resource management planning
- B . Program risk mitigation
- C . Resource interdependency management
- D . Project resource planning
Coupling with electrical circuits can create inductive interference to telecommunications facilities.
Which of the following can decrease the coupling effect?
- A . Decrease the exposure length
- B . Make sure that the single-phase components add in phase
- C . Decrease the physical separation
- D . Increase the earth resistance
XYZ Company hires you to make its transitioning procedure more effective in meeting close-out requirements. You review XYZ’s transitioning procedures to eliminate any that do not belong in the close-out phase.
Which of the following procedures should you removed?
- A . Managing the transition from the "As-ls" state to the "To-Be" or Target Stale
- B . Reviewing the status of benefits with the stakeholders and program sponsor
- C . Managing any required transition to operations
- D . Documenting lessons learned in the organizational database
When sizing an underground entrance facility, what is the MINIMUM amount of 103 metric designator conduits (4 trade size) that should be specified by the ICT distribution design?
- A . 2 Conduits
- B . 3 Conduits
- C . 4 Conduits
- D . 6 Conduits
The transfer of unwanted signals may occur over one path or several paths.
What method addresses the mitigation or suppression of unwanted signals?
- A . Mounting heights in racks and cabinets
- B . Bonding and grounding
- C . Signal coupling
- D . The use of unshielded cables
An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building C. Both ends are terminated with SC connectors.
What is the loss budget for the above fiber link?
- A . 2.95 dB
- B . 3.40dB
- C . 3.90 dB
- D . 4.35 dB
The type of apparatus housed in ERs vary greatly in size, purpose and function.
Which two of the following active equipment is included? (Choose two.)
- A . Cross-connect facilities
- B . Telecommunications equipment
- C . Environmental controls
- D . Lighting controls
- E . Building system equipment