Based on the SAP Activate methodology, which of the following testsare formal, and therefore must be documented during implementation? Note: There are 2 correct answers to this question.
Based on the SAP Activate methodology, which of the following testsare formal, and therefore must be documented during implementation? Note: There are 2 correct answers to this question.
A . Unit test
B . Business process test
C . String test
D . Integration test
Answer: B, D