Based on current trends, how many hours will be expended at project completion?

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete.

Based on current trends, how many hours will be expended at project completion?
A . 16,215
B . 14,201
C . 12,000
D . 10,526

Answer: B

Explanation:

To estimate the total hours to be expended at project completion, you can use the formula:

Estimate at Completion (EAC)=Total Budgeted HoursCPItext{Estimate at Completion (EAC)} = frac{text{Total Budgeted

Hours}}{text{CPI}}Estimate at Completion (EAC)=CPITotal Budgeted Hours Using the CPI calculated in Question 39:

EAC=12,0000.84≈14,201 hourstext{EAC} = frac{12,000}{0.84} approx 14,201 text{ hours}EAC=0.8412,000≈14,201 hours

So, the correct answer is B. 14,201 hours.