Exam4Training

Auldhouse MSPF Managing Successful Programmes Foundation Online Training

Question #1

Which of the following statements about the programme management environment is true?

1) Programmes respond to economic influences on corporate strategies

2) Programmes initiate, monitor and align the projects

  • A . Only 1 is true
  • B . Only 2 is true
  • C . Both land 2are true
  • D . Neither 1 or 2 is true

Reveal Solution Hide Solution

Correct Answer: C
Question #2

Which part of the scope of programme quality is MOST likely to be concerned with making best use of skills and experience?

  • A . Standards management
  • B . People management
  • C . Process management
  • D . Communications management

Reveal Solution Hide Solution

Correct Answer: B
Question #3

What programme role is MOST likely to also have a role within a project board to represent the interests of the business?

  • A . Programme Office
  • B . Programme Manager
  • C . Programme Board
  • D . Business Change Manager

Reveal Solution Hide Solution

Correct Answer: D
Question #4

Which information is included in Benefit Profiles?

  • A . Scheduled reviews
  • B . Dependent capabilities
  • C . Procedures to avoid double counting
  • D . Information audit requirements

Reveal Solution Hide Solution

Correct Answer: B
Question #4

Which information is included in Benefit Profiles?

  • A . Scheduled reviews
  • B . Dependent capabilities
  • C . Procedures to avoid double counting
  • D . Information audit requirements

Reveal Solution Hide Solution

Correct Answer: B
Question #4

Which information is included in Benefit Profiles?

  • A . Scheduled reviews
  • B . Dependent capabilities
  • C . Procedures to avoid double counting
  • D . Information audit requirements

Reveal Solution Hide Solution

Correct Answer: B
Question #7

Aligns the programme with corporate strategy

  • A . Only 1 is true
  • B . Only 2 is true
  • C . Both 1 and 2 are true
  • D . Neither 1 or 2 is true

Reveal Solution Hide Solution

Correct Answer: D
Question #8

What role is responsible for tracking the progress of risk responses?

  • A . Risk actionee
  • B . Risk Manager
  • C . Risk owner
  • D . Design Authority

Reveal Solution Hide Solution

Correct Answer: C
Question #9

Which label refers to one of the organizational risk perspectives?

  • A . Operational
  • B . Political
  • C . Portfolio
  • D . Economic

Reveal Solution Hide Solution

Correct Answer: A
Question #10

Which should be done during the process Closing a Programme?

  • A . Confirm that key stakeholders are satisfied with the improvements
  • B . Provide an opportunity to plan a post-project review
  • C . Identify the need for future assessment of benefit realization
  • D . Enable all outstanding risks to be closed

Reveal Solution Hide Solution

Correct Answer: C

Question #11

Which is a trigger for a compliance programme?

  • A . The corporate board has created a vision for change
  • B . A number of stand-alone projects would benefit from better coordination
  • C . The organization has to change to meet requirements of new legislation
  • D . The organization chooses to take a new innovative approach to product development

Reveal Solution Hide Solution

Correct Answer: C
Question #12

Which is a governance theme?

  • A . Identifying a Programme
  • B . Planning and Control
  • C . Risk Management Cycle
  • D . Managing the Tranches

Reveal Solution Hide Solution

Correct Answer: B
Question #13

What type of programme is sometimes referred to as a must do programme?

  • A . Vision-led
  • B . Emergent
  • C . Compliance
  • D . Specification-led

Reveal Solution Hide Solution

Correct Answer: C
Question #14

What does the I stand for in POTI, the model that helps with Blueprint development?

  • A . Investment
  • B . Implementation
  • C . Induction
  • D . Information

Reveal Solution Hide Solution

Correct Answer: D
Question #15

Which is represented in a summary risk profile?

  • A . Category of risk response
  • B . Impact of an issue
  • C . Likelihood of a risk
  • D . Cause of a risk

Reveal Solution Hide Solution

Correct Answer: C
Question #15

Which is represented in a summary risk profile?

  • A . Category of risk response
  • B . Impact of an issue
  • C . Likelihood of a risk
  • D . Cause of a risk

Reveal Solution Hide Solution

Correct Answer: C
Question #15

Which is represented in a summary risk profile?

  • A . Category of risk response
  • B . Impact of an issue
  • C . Likelihood of a risk
  • D . Cause of a risk

Reveal Solution Hide Solution

Correct Answer: C
Question #18

Include the costs for tools to track and report on progress,

  • A . Only 1 is true
  • B . Only 2 is true
  • C . Both 1 and 2 are true
  • D . Neither 1 or 2 is true

Reveal Solution Hide Solution

Correct Answer: B
Question #19

What role description includes support for project assurance and health checks which is independent of the projects?

  • A . Programme Manager
  • B . Business Change Manager
  • C . Senior Responsible Owner
  • D . Programme Office

Reveal Solution Hide Solution

Correct Answer: D
Question #20

Which is evidenced by the Business Case?

  • A . Continuing affordability of the programme
  • B . Responsibility for managing the Business Change Team
  • C . Information about what will be subject to review
  • D . Risk responses for the initial programme risks

Reveal Solution Hide Solution

Correct Answer: A

Question #21

Which is ensured by the Business Change Manager in the process Realizing the Benefits?

  • A . Optimal running of the programme verified by audits and reviews
  • B . Effective benefits realization through creating a Benefits Management Strategy
  • C . Readiness of the organization to implement the changes
  • D . Alignment of project scope with benefits realization

Reveal Solution Hide Solution

Correct Answer: C
Question #22

What is the step in the Benefits Management Cycle that includes carrying out activities to transition the capabilities delivered by the projects into outcomes?

  • A . Deliver benefits realization
  • B . Identify benefits
  • C . Develop the benefits management approach
  • D . Plan benefits realization

Reveal Solution Hide Solution

Correct Answer: A
Question #22

What is the step in the Benefits Management Cycle that includes carrying out activities to transition the capabilities delivered by the projects into outcomes?

  • A . Deliver benefits realization
  • B . Identify benefits
  • C . Develop the benefits management approach
  • D . Plan benefits realization

Reveal Solution Hide Solution

Correct Answer: A
Question #22

What is the step in the Benefits Management Cycle that includes carrying out activities to transition the capabilities delivered by the projects into outcomes?

  • A . Deliver benefits realization
  • B . Identify benefits
  • C . Develop the benefits management approach
  • D . Plan benefits realization

Reveal Solution Hide Solution

Correct Answer: A
Question #25

Should include all possible constraints

  • A . Only 1 is true
  • B . Only 2 is true
  • C . Both land 2are true
  • D . Neither 1 or 2 is true

Reveal Solution Hide Solution

Correct Answer: D
Question #26

What role focuses on ensuring appropriate ownership of risks relating to external events beyond the boundaries of the programme?

  • A . Risk owner
  • B . Programme Manager
  • C . SeniorResponsibleOwner
  • D . Risk actionee

Reveal Solution Hide Solution

Correct Answer: C
Question #27

Which activity includes addressing the disadvantages of doing nothing to those stakeholders that object to the programme?

  • A . Analyse stakeholders
  • B . Sum ma rise risks
  • C . Carry out a health check
  • D . Conduct a visioning workshop

Reveal Solution Hide Solution

Correct Answer: D
Question #28

Which is a responsibility of the Programme Manager?

  • A . Approves programme’s progression to next tranche
  • B . Defines risk thresholds for the programme’s projects
  • C . Ensures appropriate programme assurance is in place
  • D . Reports regularly on programme progress

Reveal Solution Hide Solution

Correct Answer: D
Question #29

Which is NOT representative of the programme management principles?

  • A . Allow flexibility in how the programme is managed
  • B . Provide a clearly defined set of rules and procedures
  • C . Embrace all types of programmes
  • D . Encompass best practice and lessons learned

Reveal Solution Hide Solution

Correct Answer: B
Question #30

What process provides the outputs required to deliver the Blueprint?

  • A . Managing the Tranches
  • B . Delivering the Capability
  • C . Benefits Management
  • D . Realizing the Benefits

Reveal Solution Hide Solution

Correct Answer: B

Question #31

Which is NOT a programme management principle?

  • A . Envisioning and communicating a better future
  • B . Adding value
  • C . Designing and delivering a coherent capability
  • D . Defining roles

Reveal Solution Hide Solution

Correct Answer: D
Question #32

Which is a purpose of a summary risk profile?

  • A . Explain the programme risk exposure in monetary terms
  • B . Show the relationship between critical risks in a programme
  • C . Highlight any low probability benefits that are being managed as opportunity risks
  • D . Determine the residual risk exposure, assuming that planned mitigation actions are successful

Reveal Solution Hide Solution

Correct Answer: B
Question #33

Which describes an impact of a risk?

  • A . Effect on the programme if something goes wrong
  • B . An event that might increase a programme’s outcome
  • C . The amount of risk that will be tolerated
  • D . Possibility that something will go wrong

Reveal Solution Hide Solution

Correct Answer: A
Question #34

Which is an example of a programme resource?

  • A . Configuration management
  • B . Benefit
  • C . Process
  • D . Funding

Reveal Solution Hide Solution

Correct Answer: D
Question #35

Which is a description of a programme resource?

  • A . The objective of a programme
  • B . A process to control a programme
  • C . A logical grouping of projects within a programme
  • D . An input required by a programme

Reveal Solution Hide Solution

Correct Answer: D
Question #36

What document defines the performance measures that will show whether a benefit is being realized?

  • A . Blueprint
  • B . Benefits Management Strategy
  • C . Vision Statement
  • D . Benefit Profile

Reveal Solution Hide Solution

Correct Answer: D
Question #37

Which is NOT a core element of successful communications?

  • A . Mechanism for stakeholder feedback
  • B . System to deliver messages
  • C . Method for understanding stakeholders
  • D . Tool to maintain a clear audit trail

Reveal Solution Hide Solution

Correct Answer: D
Question #38

Which is one of the three core concepts of the MSP framework?

  • A . Sponsoring Group
  • B . Vision
  • C . Principles
  • D . Risk management

Reveal Solution Hide Solution

Correct Answer: C
Question #39

Which statement relates to preparing the programme plan?

  • A . Defining the approach to risk management
  • B . Describing deliverables to be produced in Defining a Programme
  • C . Appointing the Senior Responsible Owner
  • D . Processing large amounts of information

Reveal Solution Hide Solution

Correct Answer: D
Question #39

Which statement relates to preparing the programme plan?

  • A . Defining the approach to risk management
  • B . Describing deliverables to be produced in Defining a Programme
  • C . Appointing the Senior Responsible Owner
  • D . Processing large amounts of information

Reveal Solution Hide Solution

Correct Answer: D

Question #39

Which statement relates to preparing the programme plan?

  • A . Defining the approach to risk management
  • B . Describing deliverables to be produced in Defining a Programme
  • C . Appointing the Senior Responsible Owner
  • D . Processing large amounts of information

Reveal Solution Hide Solution

Correct Answer: D
Question #42

Audit trail is established

  • A . Only 1 is true
  • B . Only 2 is true
  • C . Both land 2are true
  • D . Neither 1 or 2 is true

Reveal Solution Hide Solution

Correct Answer: A
Question #43

Which is a governance area of focus for the Programme Manager in consultation with other stakeholders?

  • A . Providing support for governance assurance reviews
  • B . Initiating assurance reviews of programme viability
  • C . Providing business intelligence for Stakeholder Profiles
  • D . Designing the programm s governance arrangements

Reveal Solution Hide Solution

Correct Answer: D
Question #44

What document describes a programme s projects, their timescales and dependencies?

  • A . Project brief
  • B . Highlight report
  • C . Blueprint
  • D . Projects Dossier

Reveal Solution Hide Solution

Correct Answer: D
Question #45

Which is a focus of the Programme Office in managing risks and issues?

  • A . Accountable for the management and control of all aspects of the risks assigned to them
  • B . Responsible for the implementation of risk response actions
  • C . Monitors and reports on business performance issues
  • D . Maintains the Risk Register and Issue Register

Reveal Solution Hide Solution

Correct Answer: D
Question #46

What role has a focus on leading reviews and ensuring adequate assurance is designed into controls?

  • A . Senior Responsible Owner
  • B . Programme Manager
  • C . Business Change Manager
  • D . Programme Office

Reveal Solution Hide Solution

Correct Answer: A
Question #47

Which is an outcome?

  • A . Product developed by a project
  • B . Measured operational improvement
  • C . Products transitioned into live use
  • D . New service ready for handover

Reveal Solution Hide Solution

Correct Answer: C
Question #48

Which is a transformational flow process?

  • A . Leading change
  • B . Adding value
  • C . Benefits Management
  • D . Realizing the Benefits

Reveal Solution Hide Solution

Correct Answer: D
Exit mobile version