Question #11
Which is a trigger for a compliance programme?
- A . The corporate board has created a vision for change
- B . A number of stand-alone projects would benefit from better coordination
- C . The organization has to change to meet requirements of new legislation
- D . The organization chooses to take a new innovative approach to product development
Correct Answer: C
Question #12
Which is a governance theme?
- A . Identifying a Programme
- B . Planning and Control
- C . Risk Management Cycle
- D . Managing the Tranches
Correct Answer: B
Question #13
What type of programme is sometimes referred to as a must do programme?
- A . Vision-led
- B . Emergent
- C . Compliance
- D . Specification-led
Correct Answer: C
Question #14
What does the I stand for in POTI, the model that helps with Blueprint development?
- A . Investment
- B . Implementation
- C . Induction
- D . Information
Correct Answer: D
Question #15
Which is represented in a summary risk profile?
- A . Category of risk response
- B . Impact of an issue
- C . Likelihood of a risk
- D . Cause of a risk
Correct Answer: C
Question #15
Which is represented in a summary risk profile?
- A . Category of risk response
- B . Impact of an issue
- C . Likelihood of a risk
- D . Cause of a risk
Correct Answer: C
Question #15
Which is represented in a summary risk profile?
- A . Category of risk response
- B . Impact of an issue
- C . Likelihood of a risk
- D . Cause of a risk
Correct Answer: C
Question #18
Include the costs for tools to track and report on progress,
- A . Only 1 is true
- B . Only 2 is true
- C . Both 1 and 2 are true
- D . Neither 1 or 2 is true
Correct Answer: B
Question #19
What role description includes support for project assurance and health checks which is independent of the projects?
- A . Programme Manager
- B . Business Change Manager
- C . Senior Responsible Owner
- D . Programme Office
Correct Answer: D
Question #20
Which is evidenced by the Business Case?
- A . Continuing affordability of the programme
- B . Responsibility for managing the Business Change Team
- C . Information about what will be subject to review
- D . Risk responses for the initial programme risks
Correct Answer: A