After optimizing the network, which of the following would be required?

Users have been experiencing slow network response times, and management has asked the network technician to provide evidence of network improvement.

After optimizing the network, which of the following would be required?
A . IDF/MDF documentation
B . Change management
C . Performance baseline
D . Physical diagram

Answer: C

Latest N10-007 Dumps Valid Version with 601 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments