A schedule's late dates are calculated during the:
A schedule's late dates are calculated during the:A . Loop calculationsB . Backward passC . Forward passD . FloatView AnswerAnswer: B Explanation: The backward pass is a technique used in project scheduling to calculate the latest possible start and finish dates for each activity without delaying the project. It starts...
The four steps to writing are:
The four steps to writing are:A . Introduction, paragraph, conclusion, works citedB . Start, write, complete, reviseC . Abstract, body conclusion, bibliographyD . Plan, write, cool, reviseView AnswerAnswer: D Explanation: The four steps to writing effectively are: Plan: Outline your ideas and structure before starting to write. Write: Draft your...
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of...
Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)
Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)A . ACWP/BCWSB . BCWS/BCWPC . ACWP/BCWPD . BCWP/ACWPView AnswerAnswer: D Explanation: The Cost Performance Index (CPI) is a crucial metric in project management, particularly within the realm of cost control. According to the Association...
What is a basic element of work or a task that must be performed over a given period of time in order to complete a project called?
What is a basic element of work or a task that must be performed over a given period of time in order to complete a project called?A . WBS elementB . ActivityC . ResourceD . CommodityView AnswerAnswer: B Explanation: An activity is a fundamental unit of work that must be...
Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:
Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is: A. Activity ID B. WBS Code C. Resource D. Account numberView AnswerAnswer: A Explanation: An Activity ID is a unique combination of letters, numbers, or blanks that describes and...
What class of estimate is used for the preliminary design phase of a project?
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of...
What is the current schedule performance index (SPI)?
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to...
A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.
A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.A . Cost breakdown structureB . Code of accountsC . Cost estimate classificationD . Schedule identification numberView AnswerAnswer: B Explanation: A Code of Accounts is a systematic coding structure used to organize...
What is the range of unit costs?
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses. What is the range of unit costs?A . $21.57B . $26.65C . $48.22D . $485.00View AnswerAnswer: D Explanation: Without...