At the end of 30 months, copper prices will have increased by what percentage over today's price?

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. At the end of 30 months, copper prices will have increased by what percentage over today's price?A . 4.6%B...

May 7, 2025 No Comments READ MORE +

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:A . Total floatB . Remaining durationC . Free floatD . Just-in-time schedulingView AnswerAnswer: A Explanation: Total float is the amount of time that an activity can be delayed from its earliest...

May 6, 2025 No Comments READ MORE +

If a project is said to be on a "fast track program/' the fast track method is:

If a project is said to be on a "fast track program/' the fast track method is: A. Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and...

May 4, 2025 No Comments READ MORE +

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. At the end of 30 months, the final price for the piece of equipment will be:A . $328,810B ....

May 3, 2025 No Comments READ MORE +

Based on current trends, how many hours will be expended at project completion?

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to...

May 1, 2025 No Comments READ MORE +

What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal.

What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal.A . EngineerB . AlternateC . Project ManagerD . AgentView AnswerAnswer: D Explanation: An agent is a person who is legally...

April 26, 2025 No Comments READ MORE +

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. At the end of 30 months, the final price for the piece of equipment will be:A . $328,810B ....

April 25, 2025 No Comments READ MORE +

Listening to what is being said by all members of a group or audience and then summarizing or interpreting is called______________.

Listening to what is being said by all members of a group or audience and then summarizing or interpreting is called______________.A . Directive listeningB . Non-listeningC . Visual listeningD . Facilitative listeningView AnswerAnswer: D Explanation: Facilitative listening is a form of listening where the listener not only pays attention to...

April 22, 2025 No Comments READ MORE +

Budgeted cost of work scheduled is all of the following except:

Budgeted cost of work scheduled is all of the following except:A . Total costs incurred in accomplishing work in a given-time periodB . Baseline for performance measurementC . Sum of the budgets for work scheduledD . Includes portion of the budget for level-of-effort workView AnswerAnswer: A Explanation: The Budgeted Cost...