Which of the following is NOT required when performing weekly or monthly schedule updates?
- A . Percent complete.
- B . Remaining duration of activities.
- C . Actual finish of activities.
- D . Original duration of activities.
Which of the following will always describe the critical path? The path with
- A . The longest duration through the network.
- B . Zero float.
- C . Negative float.
- D . The shortest duration and negative float.
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
- A . Estimating remaining durations of activities.
- B . The correct recording of actual start dates.
- C . Making "downstream" logic revisions as required.
- D . Entering the time impacts of delays and change orders.
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
- A . Use the progressed portion of the critical path of all the updates previous to the current update.
- B . Use the progressed portion of the critical path of the baseline schedule.
- C . Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
- D . Use the forward-looking critical path of the most current updates.
An earned value-based project control system can use either of which two budgets as the basis of its
calculations?
- A . Labor hours or dollars.
- B . Direct or indirect cost.
- C . Earned or budgeted cost yearly.
- D . Linear feet or dollars.