A project manager might use a PESTLE analysis in order to:
A project manager might use a PESTLE analysis in order to:
A . mitigate all possible risks to the project.
B . identify and mitigate factors that may affect the project.
C . control technological change during the project.
D . consider team social roles in early stages of the project
Answer: B