Exam4Training

A project manager is assigned to a new project and is told they need to develop the project’s risk register. When should the project manager identify the project risks?

A project manager is assigned to a new project and is told they need to develop the project’s risk register. When should the project manager identify the project risks?
A . Identify risks only at the project’s midpoint for the stakeholders to review them
B. Ensure project team members proactively identify risks throughout the project to plan for possible response strategies
C. Identify risks at the beginning of the project because the risk posture will not change
D. Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

Answer: B

Explanation:

Risk identification should be an ongoing process throughout the project lifecycle. Encouraging project team members to proactively identify risks allows for continuous risk management and the development of appropriate response strategies as new risks emerge.

Latest PMI-RMP Dumps Valid Version with 115 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version