According to the Purdue Reference Model, at which layer would you perform manufacturing operations and control?
According to the Purdue Reference Model, at which layer would you perform manufacturing operations and control?
A . Level 0
B . Level 1
C . Level 2
D . Level 3
E . Level 4
Answer: D