Which of the following activities are associated with the closing phase of a project? (Choose two.)
Which of the following activities are associated with the closing phase of a project? (Choose two.)
A . Risk mitigation
B . Archiving of project documents
C . Tracking of expenditures
D . Lessons learned
E . Quality assurance
Answer: B,D
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 338, 339
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments
                 
	