Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
You have maintained the parameters for simple discontinuation the material master of a component .
Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
A . Back flushing
B . Material requirements planning
C . Production order release
D . Kanban
Answer: B