Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.
Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.
A . Maximum stock level
B . Purchase orders
C . Safety stock
D . Lot size
Answer: C,D
Latest C_TS422_2020 Dumps Valid Version with 80 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments