Which of the following changes would BEST satisfy the project sponsor?
The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a
project. 

Which of the following changes would BEST satisfy the project sponsor?
A . Add the project sponsor to all project email correspondence moving forward
B . Include the project sponsor in all project meetings moving forward
C . Add a new line to the communications plan to provide a weekly status report with a dashboard
D . Include the project sponsor in the daily stand-up with the entire project team
Answer: A