Which of the following is the MOST appropriate next step?
A project task has been completed ahead of schedule .
Which of the following is the MOST appropriate next step?
A . Provide the next task to the newly freed resource.
B . Communicate the success to the team.
C . Notify the project sponsor of the new completion date.
D . Update the schedule and add lag to the next task.
Answer: B