Which of the following is the FIRST step the project manager should take?
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?
A . Assess the risk register’s new items.
B . Review the task start and finish dates.
C . Obtain additional resources.
D . Analyze the assigned hours.
Answer: A