Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
A . EAC
B . BAC
C . CPI
D . ETC
Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231