Which of the following describes how the project manager should BEST determine the initial sequence and durations?
After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?
A . Use milestones identified in the project charter.
B . Use data based on past knowledge.
C . Hold a full team workshop to review the complete WB
E . Collaborate with other project managers.
Answer: A
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments
                 
	