After a quality improvement program has been successfully implemented, the greatest cost of controlling quality typically is the cost of:
After a quality improvement program has been successfully implemented, the greatest cost of controlling quality typically is the cost of:
A . failure.
B . appraisal.
C . prevention.
D . inspection.
Answer: C