When integrating a new storage solution within an existing data center, what should be done first before proceeding with the integration process?

When integrating a new storage solution within an existing data center, what should be done first before proceeding with the integration process?
A . Plan the low-level design
B . Stop all ongoing operations
C . Disconnect all existing storage devices
D . Begin configuring the solution

Answer: A

Explanation:

Planning the low-level design is essential before integrating a new storage solution to ensure seamless integration.