How can you manage all tasks that are related to that deliverable?
A project-specific deliverable is not part of the SAP Activate roadmap.
How can you manage all tasks that are related to that deliverable?
A . By creating a custom team
B . By creating a custom deliverable
C . By creating a custom release
Answer: B
Explanation:
When a project-specific deliverable is not included in the standard SAP Activate roadmap, you can manage it by creating a custom deliverable in SAP Cloud ALM. This allows for tracking tasks and milestones specific to that deliverable within the project.
Reference: SAP Cloud ALM Custom Deliverable Guide
SAP Help Portal on SAP Activate Roadmap Customization