How many roles make up the Project Board?
How many roles make up the Project Board?
A . One
B . Two
C . Three
D . Four
Answer: C
Explanation:
The Project Board within the PRINCE2® framework is made up of three key roles: the Executive, the Senior User, and the Senior Supplier. These roles represent the business, user, and supplier interests respectively, ensuring that the project’s decision-making is balanced across these three perspectives.
Reference: PRINCE2® Foundation official documentation and study materials.