For a process that is outside its upper control limit (UCL), which of the following techniques would best be used to return the process under control?
For a process that is outside its upper control limit (UCL), which of the following techniques would best be used to return the process under control?
A . Conduct a Pareto analysis
B . Plan-do-check-action (PDCA)
C . Plot histograms
D . Monitor control charts
Answer: B
Explanation:
Plan-do-check-action (PDCA) is a technique that would best be used to return a process under control when it is outside its upper control limit (UCL). PDCA is a four-step cycle of continuous improvement that involves planning a change, implementing the change, checking the results, and acting on the findings. PDCA can help identify and eliminate the root causes of variation, improve the process performance, and prevent the recurrence of problems. PDCA is also known as the Deming cycle or the Shewhart cycle.
References:
Managing Supply Chain Operations, Chapter 9: Quality Management, Section 9.3: Quality Improvement, Subsection 9.3.1: Plan-Do-Check-Act Cycle
CPIM Exam Content Manual, Module 8: Quality, Technology and Continuous Improvement, Section 8.2: Continuous Improvement, Subsection 8.2.1: Continuous Improvement Concepts, Subsubsection 8.2.1.1: Plan-Do-Check-Act Cycle