How is the weighted shortest job first (WSJF) calculated?
How is the weighted shortest job first (WSJF) calculated?
A . Job size divided by cost of delay
B . Cost of delay multiplied by job size
C . Job size multiplied by cost of delay
D . Cost of delay divided by job size
Answer: D
Explanation:
Cost of delay divided by job size