You are a Dynamics 365 for Field Service Administrator. You configure Route Scheduling Optimization (RSO) and publish the schedule.

One of your schedulers indicates two of their resources are not getting work orders assigned.

You need to determine Auto Geo Code Addresses to Yes in Field Servicrk orders through RSO.

Which three options should you choose? Each correct answer presents a complete solution.
A . Work Hours is not properly configured for days being optimized.
B . Optimize Schedule field is not set to Yes.
C . The Work Location field is not set to Onsite.
D . Scheduling Method is not set to Optimize.
E . Start Location and End Location fields are not the same.

Answer: ABE

Explanation:

https://docs.microsoft.com/en-us/dynamics365/field-service/rso-faq