Which of the following should be modified to prevent the issue from reoccurring?
A disaster recovery team learned of several mistakes that were made during the last disaster recovery parallel test. Computational resources ran out at 70% of restoration of critical services.
Which of the following should be modified to prevent the issue from reoccurring?
A . Recovery point objective
B. Recovery time objective
C. Mission-essential functions
D. Recovery service level
Answer: D
Explanation:
Reference: https://www.nakivo.com/blog/disaster-recovery-in-cloud-computing/