Which three options should you configure?
A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.
The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling m a graphical view.
You need to configure the system to meet the requirements.
Which three options should you configure? Each answer presents a partial solution. NOTE: Each correct selection is worth one point
A . finite capacity
B. Capable to Promise
C. bottleneck resource
D. job scheduling
E. operations scheduling
Answer: A,C,D