Based on the SAP Activate methodology, which of the following testsare formal, and therefore mustbe documented during implementation?
Based on the SAP Activate methodology, which of the following testsare formal, and therefore mustbe documented during implementation?
Note: There are 2 correct answers to this question.
A . Unit test
B. Business process test
C. Integration test
D. String test
Answer: B,C