What needs to happen when new detailed requirements are added to a timebox?
What needs to happen when new detailed requirements are added to a timebox?
A . Requirements of a similar level of effort should be removed
B. More people should be added to the delivery team
C. The delivery milestones should be reviewed and re-planned
D. Formal change control should be applied
Answer: A