What should be emphasized when tailoring the PRINCE2 Progress theme?
What should be emphasized when tailoring the PRINCE2 Progress theme?
A . Monitoring what is being delivered
B. Tracking time and cost
C. Planning resources
D. Assessing the impact of risks
Answer: A