- All Exams Instant Download
Which of the following criteria is not a sensible criterion for prioritization?
One activity in managing requirements includes prioritization of the requirements.
Which of the following criteria is not a sensible criterion for prioritization? (1 Point)
A . The impact on the existing operational system (operating environment)
B. The influence on the overall success of the business
C. The effort for the validation of the requirements
D. The costs resulting from the implementation of the requirements
E. Which requirements must be implemented in which release
Answer: C
Latest IREB_CPRE_FL Dumps Valid Version with 45 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments