Which of the following should be an IS auditor’s GREATEST consideration when scheduling follow-up activities for agreed-upon management responses to remediate audit observations?
Which of the following should be an IS auditor’s GREATEST consideration when scheduling follow-up activities for agreed-upon management responses to remediate audit observations?
A . Business interruption due to remediation
B. IT budgeting constraints
C. Availability of responsible IT personnel
D. Risk rating of original findings
Answer: D